RCCP Load Dashboard
ESE›Capacity Planning›RCCP
RUN-2026-047 · 09:42
5
Work Centres
in this run horizon
1
Overloaded WCs
>90% capacity used
58%
Avg Load
excl. WC-MILL (no capacity)
Delta — RUN-2026-047 vs RUN-2026-046
Work CentrePrev LoadCurr LoadDeltaTrend
WC-CAST71%78%+7%↑ Rising
WC-MACH88%96%+8%↑ Now Overloaded
WC-NEST61%54%−7%↓ Improving
WC-WELD70%67%−3%↓ Improving
WC-MILL———No capacity
Work Centre Load vs Capacity — RUN-2026-047
OK (<80%) Near limit (80–90%) Overloaded (>90%)
▶ RCCP Warnings 2 (click to expand)
WC-CAST
WC-MACH
WC-NEST
WC-WELD
Load intensity:
0%80%100%+
· Click any cell to view jobs
As of RUN-2026-047 · Fri 4 Jul 2026, 09:42 · Horizon: Jun 30 – Jul 15, 2026
8
Pending EUs
not yet scheduled
2
Overdue
required date passed
1
Red Card (P0)
priority override active
4.2d
Avg Days Left
to required date
EUs by Work Centre
PriorityIndent#ItemWork CentreDurationRequired DateDays LeftLast DecisionActions
Last run: Today 09:42 · Next scheduled: 16:00